This website uses cookies to ensure you get the best experience on our website. Learn more

Appleby v Myers [1867] LR 2 CP 651

By Oxbridge Law TeamUpdated 04/01/2024 06:59

Judgement for the case Appleby v Myers

KEY POINTS

  • The parties' contractual agreement outlined mutual obligations, expecting complete performance within a set timeframe. However, unforeseen misfortune disrupted execution beyond the parties' control, impeding the fulfillment of their roles as envisioned. 

  • The legal question arises: Can the doctrine of complete performance be excused due to uncontrollable misfortune? This prompts a complex examination of contractual enforcement, questioning whether external factors justify deviation from the contract's strict performance requirement. Resolution hinges on legal interpretation and applicable principles in the jurisdiction.

FACTS

  • A (‘Plaintiffs’) entered into a contract with B (‘Defendant’) to perform work and supply materials on B's premises for a specified sum. The agreement stipulated that payment would be made upon completing the work, with no entitlement for A to recover any amount until the project was finished.

  • An exception to this payment condition could be invoked if A could demonstrate that B's default had prevented the performance of the contract.

  • The specific nature of the contract involved the erection of machinery on the Defendant's premises, with prices assigned for portions of the work. Additionally, A was obligated to keep the machinery in repair for two years.

  • Payment for the entirety of the work was to be made upon the completion of the entire project. At a point in the project timeline, some portions of the work and others were completed.

  • Unexpectedly, the premises and all the machinery and materials suffered destruction due to an accidental fire.

JUDGEMENT

  • The Court of Common Pleas' previous judgment was reversed.

  • It was held that both parties were excused from further contract performance.

  • However, the plaintiffs were not entitled to pursue legal action concerning those portions of the work that had been completed, regardless of whether the materials used had become the property of the defendant or not.

COMMENTARY

  • The unforeseen misfortune, acting as a disruptive force beyond the parties' control, adds a layer of complexity to fulfilling their envisioned roles in the agreement.

  • The crux of the legal dilemma lies in whether the doctrine of complete performance can be excused in the face of such uncontrollable misfortune. This question initiates a thorough examination of contractual enforcement, delving into whether external factors justify a departure from the strict performance requirement outlined in the contract. The eventual resolution is contingent upon the nuanced interpretation of legal principles within the jurisdiction.

  • In the context of the case's legal proceedings, reversing the Court of Common Pleas' prior judgment signals a shift in the legal landscape. The ruling acknowledges that both parties are absolved from further contractual performance due to the encountered misfortune. However, a noteworthy limitation is placed on the plaintiff's ability to pursue legal action for completed portions of the work. This restriction applies irrespective of whether the materials utilized in these completed portions had become the Defendant's property.

  • The legal intricacies of this decision highlight the balancing act between excusing performance based on external factors and delineating the scope of legal recourse for parties involved in disrupted contracts.

ORIGINAL ANALYSIS

  • Plaintiff agreed to build a steam engine for Defendant’s premises, with the contract dividing the work into 10 parts and stating the price for each and another term stating that Plaintiff undertook to build every part of the project.

  • When all parts were in an advanced state, a fire burnt down the premises.

  • The court held that the contract was frustrated but that neither had a cause of action (i.e. Plaintiff could NOT recover for expenses). 

Blackburn J

  • In this contract it was agreed that Defendant would pay nothing until completion. Had the fire left the premises untouched but damaged one part of the work, Plaintiff would have had to replace it at its own expenses.

  • Under the Taylor v Caldwell principle, Plaintiff is excused from completing the work but are not entitled to any compensation, It is akin to a case where a ship owner has been unable to deliver goods due to unexpected perils and is excused performance but may not claim compensation for the expenses of part-performance.

  • Plaintiff can recover nothing because payment is only due on completion, as the contract stated.

Any comments or edits about this case? Get in touch

For Further Study on Appleby v Myers

Contract Law Notes
1,511 total pages
748 purchased

Contract law notes fully updated for recent exams at Oxford and Cambrid...

Need instant answers? Our AI exam tutor is here to help.

Ask questions 🙋 Get answers 📔 It's simple 👁️👄👁️

Our AI is educated by the highest scoring students across all subjects and schools. Join hundreds of your peers today.

Get Started
Claim every advantage to get a first in law
Contract Law Notes
1,511 total pages
748 purchased

Contract law notes fully updated for recent exams at Oxford and Cambrid...