Metropolitan Water Bd v Dick Kerr [1918] AC 119

By Oxbridge Law TeamUpdated 04/01/2024 06:59

Judgement for the case Metropolitan Water Bd v Dick Kerr

Table Of Contents

Lord Dunedin

  • Held that the term regarding delays and difficulties “whatsoever and however occasioned” did not include indefinite delay.

  • It would be absurd to apply it to the present situation of a bar on further construction.

Lord Parmoor

  • Says indefinite postponement could not have been in the contemplation of the parties when making this clause. 

Any comments or edits about this case? Get in touch

For Further Study on Metropolitan Water Bd v Dick Kerr

Contract Law Notes
1,511 total pages
747 purchased

Contract law notes fully updated for recent exams at Oxford and Cambrid...

Need instant answers? Our AI exam tutor is here to help.

Ask questions 🙋 Get answers 📔 It's simple 👁️👄👁️

Our AI is educated by the highest scoring students across all subjects and schools. Join hundreds of your peers today.

Get Started
Claim every advantage to get a first in law
Contract Law Notes
1,511 total pages
747 purchased

Contract law notes fully updated for recent exams at Oxford and Cambrid...